Ventura Avenue Improvements - Paulin Drive to Bicentennial Way

Estimated Construction Schedule: Slated to begin February, 2014 and is anticipated to be completed July, 2014.
Construction Contract Amount: $843,467
Project ID #: 747

Description: This project will construct roadway and utility improvements along Ventura Avenue from Bicentennial Way to Paulin Drive. The utility inprovements will consist of replacing the existing sewer facilities, selected water services, and upgrading a portion of the storm drain system. Roadway improvements will consist of reconstructing the existing pavement and widening the roadway along the east side of Ventura Avenue from Russell Drive to Bicentennial Way.



Current Activity: All roadway and Utility work has been successfully completed.

Contacts:

Clay Thistle
Associate Civil Engineer
City of Santa Rosa
(707)543-3855
CThistle@srcity.org

Vern Tyree
Construction Inspector
Coastland Civil Engineering
(707) 479-7055
tyree@coastlandcivil.com

Mimi Arvin
Inspector
City of Santa Rosa
(707) 543-3914

Kevin Rowe
Project Manager
Argonaut Constructors
(707)542-4862

Steve Tusi
Superintendent
Argonaut Constructors
(707)542-4862

Correspondence:
Advance Project Notice 10-01-13
Imminent Construction Notice 02-18-14
Contractor's Notification Letter 02-19-14
Detour Notice 03-04-14
Sonoma County Transit Public Notice 3-10-14


Measure M Image

Click for larger image
Project Image
Note: All dates and times are subject to change.